Microsoft’s 80 Million Tonnes of Removals: What a Five to Eight Year Lead Time Means for Buyers
Microsoft reports offtakes for 80 million tonnes of removal since 2023 and says new capacity takes five to eight years to reach its first credit. Climate Decode sets that interval against SBTi V2.0, project financing and the contract terms buyers can adopt.
At a Glance · Microsoft’s Removal Offtakes
|
Contracted 80 MILLION TONNES Microsoft signed offtakes for 80 million tonnes between June 2023 and summer 2026, mainly BECCS and afforestation, reforestation and revegetation.1 The largest single contracts are with BTG Pactual, Chestnut Carbon and Fidelis for AtmosClear.24 |
Lead time FIVE TO EIGHT YEARS The interval from deciding to anchor new capacity to the first credit, built up stage by stage in Microsoft’s paper.2 |
Delivered ABOUT 3% The share of durable tonnes contracted by all buyers that CDR.fyi counts as delivered.3 |
Microsoft’s paper records 80 million tonnes contracted since June 2023, and its January 2026 portfolio update lists BTG Pactual (8.0 million tonnes), Chestnut Carbon (7.4 million tonnes) and Fidelis for AtmosClear (6.8 million tonnes) as the three largest contracts,24 against a five to eight year interval to the first credit, and CDR.fyi counts only about 3% of durable tonnes contracted as delivered, so that the contracted figure describes future supply while the lead time determines who can rely on it.1, 3
SBTi’s Net-Zero Standard V2.0 requires Category A companies with a net-zero target to support eligible removals from 2035, and as a programme begun in 2027 would on Microsoft’s intervals reach its first credit between 2032 and 2035, buyers that have not yet started have the least room for delivery setbacks.4
Microsoft’s take-or-pay contracts give lenders evidence of future revenue, as in Terradot’s financing of up to USD 34 million, although BloombergNEF reports its 2026 contracting about 80% below the same period of 2025, so that buyers should adopt its portfolio, criteria and contract terms without assuming that any single buyer’s demand continues.5, 6
|
1
|
What Microsoft Has Contracted |
Microsoft’s CDR Lessons Learned 2026 paper states that it signed offtakes for 80 million tonnes of additional carbon dioxide removal between June 2023 and summer 2026, and that purchases by buyers other than Microsoft and the Frontier coalition rose about 50% from 2024 to 2025,1 as Green Earth reported on 28 October 2026.7 The portfolio is concentrated in bioenergy with carbon capture and storage (BECCS) and in afforestation, reforestation and revegetation (ARR),8 and Microsoft’s January 2026 update lists 60 projects with 78.3 million tonnes of active contracts, of which ARR holds 29.4 million tonnes and BECCS 24.3 million tonnes (Table 1).9
| Pathway | Projects | Contracted, million tonnes | Share of total |
|---|---|---|---|
| ARR | 12 | 29.40 | 37.6% |
| BECCS | 10 | 24.28 | 31.0% |
| Improved forest management | 12 | 7.82 | 10.0% |
| Soil carbon | 5 | 5.54 | 7.1% |
| BiCRS | 1 | 4.92 | 6.3% |
| Agroforestry | 3 | 3.53 | 4.5% |
| Biochar | 6 | 1.57 | 2.0% |
| Direct air capture | 3 | 0.82 | 1.0% |
| CO2 mineralisation | 2 | 0.32 | 0.4% |
| Enhanced rock weathering | 6 | 0.10 | 0.1% |
| Total | 60 | 78.29 | 100% |
Table 1 · Microsoft’s active carbon removal contracts by pathway, to 20 January 2026. Source: Microsoft, Updating our Carbon Removal Portfolio, January 2026, pp. 3 to 6; tonnages summed by Climate Decode, excluding the Rubicon Carbon framework listed as up to 18 million tonnes.
Based on information the company has reported publicly.
The January 2026 update lists each contract by supplier and project, so that the tonnes behind Table 1 can be attributed to named counterparties, and the 15 largest of the 60 projects, which together account for 58.0 million of the 78.3 million tonnes, are set out in Table 2.24 The list is ordered by contracted tonnes and omits the Rubicon Carbon Framework for Nature-based Carbon Removal, which Microsoft records as up to 18 million tonnes and which is not included in the 78.3 million tonne subtotal. Below the 15 largest, the same tables record Living Carbon (ARR, United States, 1,407,927 tonnes), Exomad Green (biochar, Bolivia, 1,240,000 tonnes), Hafslund Celsio (BECCS, Norway, 1,120,000 tonnes), Ørsted Avedore Power Station (BECCS, Denmark, 1,000,000 tonnes), 1PointFive Stratos (direct air capture, United States, 500,000 tonnes), Heirloom (direct air capture, United States, 315,000 tonnes) and Terradot Project Carcará (enhanced rock weathering, Brazil, 3,000 tonnes).25
| Project (supplier, project) | Project type | Storage | Country | Contracted tonnes | Signed (Microsoft fiscal year) | Source |
|---|---|---|---|---|---|---|
| BTG Pactual Timberland Investment Group, Reforestation and Restoration Strategy | ARR (reforestation) | Biological, standing forest | Brazil | 8,000,000 | FY2024 | Microsoft, January 2026, p. 4 |
| Chestnut Carbon, Sustainable Restoration Megaton Project | ARR (reforestation) | Biological, standing forest | United States | 7,444,588 | FY2025 | Microsoft, January 2026, p. 5 |
| Fidelis, AtmosClear | BECCS | Geological | United States | 6,787,500 | FY2025 | Microsoft, January 2026, p. 5 |
| Vaulted Deep, US Portfolio | BiCRS | Geological, deep well injection | United States | 4,915,000 | FY2025 | Microsoft, January 2026, p. 6 |
| CO280, Pulp & Paper BECCS | BECCS | Geological | United States | 3,695,000 | FY2025 | Microsoft, January 2026, p. 5 |
| C2X, Beaver Lake | BECCS | Geological | United States | 3,600,000 | FY2026 to 20 January | Microsoft, January 2026, p. 6 |
| re.green, Amazon and Atlantic Reforestation Project Expansion | ARR (reforestation) | Biological, standing forest | Brazil | 3,484,435 | FY2025 | Microsoft, January 2026, p. 4 |
| Stockholm Exergi, Vartan | BECCS | Geological | Sweden | 3,330,000 | FY2024 | Microsoft, January 2026, p. 4 |
| re.green, Amazon and Atlantic Reforestation Project | ARR (reforestation) | Biological, standing forest | Brazil | 3,000,000 | FY2024 | Microsoft, January 2026, p. 4 |
| Copenhagen Infrastructure Partners and Vestforbrænding, Gaia | BECCS | Geological | Denmark | 2,950,000 | FY2026 to 20 January | Microsoft, January 2026, p. 6 |
| Indigo Carbon, US Project No. 1 (2025 CRUPA) | Soil carbon | Biological, soil | United States | 2,850,000 | FY2026 to 20 January | Microsoft, January 2026, p. 6 |
| Anew Climate, Cumberland Gap | IFM | Biological, standing forest | United States | 2,087,783 | FY2025 | Microsoft, January 2026, p. 5 |
| Agoro Carbon, Pastureland Program | Soil carbon | Biological, soil | United States | 2,074,918 | FY2025 | Microsoft, January 2026, p. 5 |
| Rubicon Carbon, Kijani Smallholder Farmer Forestry Project | Agroforestry | Biological, trees on farms | Uganda | 2,000,000 | FY2025 | Microsoft, January 2026, p. 5 |
| Rainforest Builder, Project Buffalo | ARR (reforestation) | Biological, standing forest | Sierra Leone | 1,815,000 | FY2026 to 20 January | Microsoft, January 2026, p. 6 |
Table 2 · Microsoft’s largest removal offtakes by project, 15 largest by contracted tonnes, to 20 January 2026. Source: Microsoft, Updating our Carbon Removal Portfolio, January 2026, pp. 4 to 6; Microsoft fiscal year 2024 runs from July 2023 to June 2024 and fiscal year 2025 from July 2024 to June 2025; pathways as classified by Microsoft; the 58.0 million tonne sum of the 15 rows is computed by Climate Decode.24 Storage class assigned by Climate Decode from the pathway: forest, farm and soil projects hold carbon in biomass or soil, while BECCS and BiCRS projects inject captured CO2 or bio-slurry into geological formations.
Based on information the companies have reported publicly.
The same update places forestry and soil pathways, which Microsoft classes as low durability, at about 59% of contracted tonnes and direct air capture at about 1%,9 with contract terms of 10 to 15 years for engineered removal and typically more than 20 years for nature-based removal, as reported by ESG Today.10
|
2
|
The Five to Eight Year Interval |
Microsoft’s paper builds the interval from stages, comprising six to twelve months to define goals, twelve to eighteen months of diligence and first contracts, up to twelve months for the developer to raise finance, 24 to 48 months to reach commercial operations and three to six months to first delivery, so that the total from programme inception to the first credit is five to eight years.2 The pathway lead times in Table 3 show where that time is spent, with BECCS and direct air capture at the long end because both require capture and storage infrastructure to be built.11
| Pathway | Development stage | Build or growth stage | Delivery profile |
|---|---|---|---|
| ARR | 1 to 2 years for land enrolment and development | 2 to 3 years of site preparation, planting and accumulation before first issuance | Parabolic |
| Improved forest management | 2 to 3 years to first issuance for an experienced developer, 3 to 4 years otherwise | Included in the interval to first issuance | Flat from year one |
| Biochar | 1 to 2 years to develop | 1 to 2 years to construct, test and commission | Ideally flat |
| BECCS | 2 to 3 years to develop | 3 to 4 years to construct, commission and deploy | Flat, within the operational envelope of the bioenergy asset |
| Direct air capture | 2 to 3 years to final investment decision after demonstration | 3 to 5 years to construct, commission and deploy | Flat, close to 100% of capacity |
| Enhanced rock weathering | 2 to 4 years to deploy and spread | 1 to 2 years more before credits | Parabolic |
Table 3 · Microsoft’s stated lead times and delivery profiles by pathway. Source: Microsoft, CDR Lessons Learned 2026, pp. 16 to 20.
Based on information the company has reported publicly.
The paper gives no delivered figure, and CDR.fyi reports that about 3% of durable tonnes contracted by all buyers have been delivered, against about 13% for buyers other than Microsoft and Frontier,3 while Senken reports about 91,000 tonnes delivered against 36.4 million tonnes of durable removal contracted to Microsoft in April 2026.12 Because Microsoft often contracts two to five years before projects are operational,13 these ratios are consistent with most projects still being in development.
Climate Decode helps buyers size the removals their targets will need, test project timelines against delivery dates, and keep an audit-ready record of each offtake.
Book a briefing → Subscribe to insights →|
3
|
Emissions, the 2030 Goal and the 2026 Slowdown |
Microsoft aims to be carbon negative by 2030 and to remove its historical emissions by 2050,14 while its fiscal 2025 emissions reached 20.3 million tonnes, up 25% from 16.2 million tonnes,15 and Climate Decode’s earlier analysis places that level 58% above the fiscal 2020 baseline, attributing much of the rise to the end of purchases of unbundled renewable energy certificates.16
Procurement slowed in 2026, since the Chief Sustainability Officer responded to April reports of a pause by saying that the program “has not ended” although pace or volume may be adjusted,14 and BloombergNEF calculated 8.55 million tonnes contracted through mid-July 2026, about 80% below the same period of 2025, a measure of contracted volume over part of a year.6 Microsoft announced in May a BECCS agreement with BioCirc for up to 650,000 tonnes over seven years, with deliveries from the second half of 2026 to 2032.17
|
4
|
What the Delay Means Under SBTi V2.0 |
SBTi published its Net-Zero Standard V2.0 on 11 June 2026, under which Category A companies with a net-zero target must support eligible removals equal to at least 1% of ongoing scope 1, 2 and 3 emissions from 2035, including a defined and increasing share of long-lived removals, and must neutralise all residual emissions with eligible removals from the net-zero target year,26 with removals verified ex post and carbon credits never counted toward target progress, as Climate Decode’s analysis of the final standard sets out.4
Applying Microsoft’s intervals, a buyer that begins procurement in 2027 can expect its first credit between 2032 and 2035 and one that begins in 2030 between 2035 and 2038, so that the first has a margin of zero to three years before 2035 and the second may reach it without delivered supply, before allowing for the permitting, financing, execution and generation delays that the paper lists.18 Because ex post verification gives a contract a right to future credits and no claim until each is issued, contracting several years ahead is the practical route to neutralisation after 2035.
|
5
|
How Forward Contracting Creates Bankable Demand |
The paper identifies bilateral, take-or-pay offtake as Microsoft’s structure and notes that developers may need up to twelve months after signature to raise capital, so that a contract signed years before operation becomes the evidence on which lenders advance funds.19 HASI’s October 2026 commitment of up to USD 34 million to Terradot, a senior secured term loan described as the largest disclosed debt financing for enhanced rock weathering, rests on fixed-price, multi-year offtakes with Frontier, and Terradot’s chief financial officer put the lender’s position as “Lenders only back what they can predict.”5
Microsoft accounted for 78.5% of disclosed durable tonnes purchased by April 2026,3 so that a developer financed on one large buyer’s contract is exposed to that buyer’s pace, which the BloombergNEF figure shows can change within a year, while public signals such as draft European Union legislation for 250 million tonnes of permanent removal procurement from 2031 to 2040 are intended to broaden the base.19
|
6
|
What Corporate Buyers Should Take From It |
Microsoft’s paper lists the questions to settle before approaching suppliers, namely how firm the need is, the tonnage, the delivery date, how demand changes and the cost guardrails agreed with finance, with the example of a buyer needing 1 to 2 million tonnes in 2033 and 4 million in 2035 that might anchor 3 million tonnes of 2033 capacity.20 Four features of Microsoft’s approach follow:
- A portfolio spread across pathways and counterparties, starting with small purchases from operating or in-development projects.20
- Written quality criteria refined each year, such as Forest Stewardship Council certification for biomass,21 and for improved forest management the criteria published with Relae in October 2026.22
- Contract terms that fix delivery thresholds, cure periods and a waterfall of remedies in advance.23
- Contracting for the 2030s alongside near-term purchases, since the paper advises buyers with targets for 2035 or later to begin now.2
Taken with the five to eight year interval, these features indicate that a buyer relying on removals under SBTi V2.0 should settle its design questions and sign first offtakes within one to two years, the window Senken suggests for securing supply for the 2030s,12 so that contracts turn a future requirement into delivered tonnes. Climate Decode’s analysis of the hyperscalers sets the same supply constraint against the net-zero pledges of Microsoft, Google, Amazon and Meta.
Climate Decode Platform
The registry figures behind Climate Decode’s removals analysis come from Canopy Market Watch, which tracks issuance, retirements, ratings and labels across ten registries.
Supply, demand and pricing across voluntary, CORSIA-eligible and Article 6 credits, by country, project type and methodology.
Open Market Watch →Canopy’s due diligence engine tests removal projects for delivery risk, durability and permanence, and keeps an audit-ready record of every purchase.
Explore Canopy →Notes
2 Microsoft, CDR Lessons Learned 2026, pp. 5 and 6, timeline from programme inception to first credit. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
3 CDR.fyi, durable CDR market update, 12 June 2026, delivery rates and Microsoft's share of disclosed durable tonnes purchased as of April 2026. https://www.cdr.fyi/blog/durable-cdr-market-update-carbon-unbound-east-coast-2026
4 Climate Decode, SBTi Net-Zero Standard V2.0 final, analysis of the standard published 11 June 2026. https://climate-decode.com/insights/vcm-series/sbti-net-zero-v2-final
5 ESG Today, Terradot secures $34 million from HASI to build ERW carbon removal projects, 29 October 2026. https://www.esgtoday.com/terradot-secures-34-million-from-hasi-to-build-erw-carbon-removal-projects/
6 Let's Data Science, Microsoft cuts carbon removal purchases amid AI expansion, summarising Bloomberg and BloombergNEF, 13 August 2026. https://letsdatascience.com/news/microsoft-cuts-carbon-removal-purchases-amid-ai-expansion-633fa644
7 Green Earth, Microsoft signs offtakes for 80 million tonnes of removals, 28 October 2026. https://www.green.earth/news/microsoft-signs-offtakes-for-80-million-tonnes-of-removals
8 Microsoft, CDR Lessons Learned 2026, p. 14, portfolio concentration in BECCS and ARR. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
9 Microsoft, Updating our Carbon Removal Portfolio, January 2026, pp. 2 to 7, contract tables to 20 January 2026 and note 2 on durability classes; tonnages by pathway summed by Climate Decode. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/Updating-our-Carbon-Removal-Portfolio.pdf
10 ESG Today, Microsoft’s Carbon Footprint Jumps 25% as AI Buildout Challenges Climate Goals, 13 July 2026, reporting Microsoft's 2026 Environmental Sustainability Report: 29 projects added in 2025 across ten pathways, and contract terms of 10 to 15 years for engineered removal and typically more than 20 years for nature-based removal. https://www.esgtoday.com/microsofts-carbon-footprint-jumps-25-as-ai-buildout-challenges-climate-goals/
11 Microsoft, CDR Lessons Learned 2026, pp. 16 to 20, pathway development and delivery profiles. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
12 Senken, Microsoft bought 80Mt of carbon removal: what can we learn, 4 November 2026. https://www.senken.io/carbon-outlook/microsoft-bought-80mt-of-carbon-removal-what-can-we-learn
13 Microsoft, Updating our Carbon Removal Portfolio, January 2026, p. 7, note 1, contracting two to five years before projects are operational. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/Updating-our-Carbon-Removal-Portfolio.pdf
14 ESG Today, Microsoft says its carbon removal program has not ended, 14 April 2026. https://www.esgtoday.com/microsoft-says-its-carbon-removal-program-has-not-ended/
15 ESG Dive, Microsoft's data center expansion drove 25% emissions spike in 2025, 13 July 2026, fiscal 2025 emissions. https://www.esgdive.com/news/microsofts-data-center-expansion-drove-25-emissions-spike-2025-environmental-sustainability-report/825082/
16 Climate Decode, Microsoft's emissions jump, The Decode, 15 July 2026, fiscal 2020 baseline of 12.9 million tonnes and the Scope 2 accounting change. https://climate-decode.com/insights/the-decode/microsoft-emissions-jump
17 ESG Today, Microsoft announces first major carbon removal deal since reportedly exiting the market, 20 May 2026. https://www.esgtoday.com/microsoft-announces-first-major-carbon-removal-deal-since-reportedly-exiting-the-market/
18 Microsoft, CDR Lessons Learned 2026, p. 7, project execution risks and contract design. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
19 Microsoft, CDR Lessons Learned 2026, pp. 5 to 7 and 13, take-or-pay offtake, developer fundraising and forward demand; footnote 18, p. 13, draft European Union legislation. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
20 Microsoft, CDR Lessons Learned 2026, p. 14, buyer design criteria and risk tolerance. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
21 Microsoft, CDR Lessons Learned 2026, p. 4 (quality criteria refined annually) and pp. 9 and 10, quality criteria and Forest Stewardship Council certification. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
22 Climate Decode, Microsoft and Relae IFM credit criteria, published 8 October 2026. https://climate-decode.com/insights/vcm-series/vcm-2026-era-of-integrity/microsoft-relae-ifm-credit-criteria
23 Microsoft, CDR Lessons Learned 2026, p. 7, delivery thresholds, cure periods and remedies. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/CDR-Lessons-Learned-2026.pdf
24 Microsoft, Updating our Carbon Removal Portfolio, January 2026, pp. 4 to 6, contract rows signed in fiscal years 2024 and 2025 and in fiscal year 2026 to 20 January 2026 (supplier, project, location, type and contracted volume); sum of the 15 rows computed by Climate Decode. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/Updating-our-Carbon-Removal-Portfolio.pdf
25 Microsoft, Updating our Carbon Removal Portfolio, January 2026, pp. 3 to 6, rows for Living Carbon, Exomad Green, Hafslund Celsio, Ørsted Avedore Power Station, 1PointFive, Heirloom and Terradot; the document contains no row for Ørsted Asnæs. https://cdn-dynmedia-1.microsoft.com/is/content/microsoftcorp/microsoft/msc/documents/presentations/CSR/Updating-our-Carbon-Removal-Portfolio.pdf
26 SBTi, Corporate Net-Zero Standard V2.0, chapter 6, Ongoing Emissions Responsibility, criteria CNZS-C45 (removals from 2035) and CNZS-C46 (neutralisation of residual emissions at the net-zero target year). https://standards.sciencebasedtargets.org/chapter/6-ongoing-emissions-responsibility
Sources
CDR.fyi: Durable CDR market update, 12 June 2026
Climate Decode: SBTi Net-Zero Standard V2.0 final, June 2026
SBTi: Corporate Net-Zero Standard V2.0, chapter 6, Ongoing Emissions Responsibility
ESG Today: Terradot secures $34 million from HASI, 29 October 2026
Let’s Data Science: summary of Bloomberg and BloombergNEF on Microsoft’s 2026 removal purchases, 13 August 2026
Green Earth: Microsoft signs offtakes for 80 million tonnes of removals, 28 October 2026
Microsoft: Updating our Carbon Removal Portfolio, January 2026
ESG Today: Microsoft’s carbon footprint jumps 25% as AI buildout challenges climate goals, 13 July 2026
Senken: Microsoft bought 80Mt of carbon removal, what can we learn, 4 November 2026
ESG Today: Microsoft says its carbon removal program has not ended, 14 April 2026
ESG Dive: Microsoft data center expansion drove 25% emissions spike, 13 July 2026
Climate Decode: Microsoft’s emissions jump, July 2026
ESG Today: Microsoft announces BioCirc BECCS deal, 20 May 2026
Climate Decode: Microsoft and Relae IFM credit criteria, 8 October 2026
Delivery ratios are from CDR.fyi and Senken and are not figures published in Microsoft’s paper; BloombergNEF’s figure measures contracted volume over part of a year. Tonnages by pathway are summed by Climate Decode from Microsoft’s published contract tables.
|